Method of Procedure (MOP)

Water Cooled Chiller Annual Preventative Maintenance

Section 01: MOP Schedule Information

MOP Title: Water Cooled Chiller Annual Preventative Maintenance
MOP Identifier:
Version:
Creation Date: 8/27/2025
Work Description: Annual Preventative Maintenance
Component Type: Water Cooled Chiller
Manufacturer: Carrier
Model Number: 19XRV5P51442LCH64S
Serial Number: SN-A47B021C
Equipment Number: CHILLER-1
Location: Data Hall 1
Duration: 6-8 hours. This timeframe allows for thorough inspection, cleaning, filter changes, lubrication, and testing, which are typical components of an annual chiller PM.
Level of Risk (LOR): Level 2 (Medium)
Single system affected with redundancy available
CET Level Required: CET-2 required to perform work
Standard mechanical maintenance work
Author:
Author CET Level:
Approver:

Section 02: Site Information

Customer: Glenart Group
Site Name: GLE-07
Data Center Location: Data Hall 1
Site Address: 2300 US-34, Oswego, IL 60543
Site Contact:

Section 03: MOP Overview

MOP Title: Water Cooled Chiller Annual Preventative Maintenance
Work Area:
Building/Floor/Room:
Access Requirements:
Self Delivered / Vendor: Self-Delivered
Qualifications Required:
  • Required Certifications:
    • EPA 608 Universal: Required for refrigerant handling
    • OSHA 10/30: General industry safety certification
  • Experience Level:
    • Minimum 5 years of experience with water-cooled chiller maintenance and repair.
Advance notifications required:
  • Data Center Manager: 24 hours advance - Approve maintenance window and coordinate resources
  • NOC/BMS Operator: 4 hours advance - Prepare monitoring systems and acknowledge alarms
  • IT Operations: 24 hours advance - Plan for any affected systems or redundancy needs
  • Security: Day of work - Arrange access and visitor badges for any contractors
Post notifications required:
  • Data Center Manager: Completion confirmation with any issues encountered
  • NOC/BMS Operator: System status update and alarm points restored to normal
  • IT Operations: All-clear notification that equipment is back online
  • Maintenance Log: Updated with work performed, readings, and next due date

Section 04: Effect of MOP on Critical Facility

Facility Equipment or System Yes No N/A Details
Electrical Utility Equipment
Emergency Generator System
Critical Cooling System Chiller is a primary component of the critical cooling system.
Ventilation System
Mechanical System The chiller is a core component of the mechanical system.
Uninterruptible Power Supply (UPS)
Critical Power Distribution System
Emergency Power Off (EPO)
Fire Detection Systems
Fire Suppression System
Monitoring System Chiller performance and status are monitored.
Control System Chiller operation is controlled by the building management system (BMS).
Security System
General Power and Lighting System
Lockout/Tagout Required? Annual preventative maintenance requires electrical and mechanical isolation.
Work to be performed "hot"?
Radio interference potential?
Water/Leak Detection System Water-cooled chiller poses a leak risk.

Section 05: Safety Requirements

REQUIRED PERSONAL PROTECTIVE EQUIPMENT (PPE)

PPE requirements specific to Carrier Water Cooled Chiller maintenance:

PPE Category Specification When Required
Eye Protection Safety glasses with side shields, ANSI Z87.1 REQUIRED - At all times during maintenance work per OSHA 29 CFR 1910.133
Hearing Protection 90dB exposure limit
Models: 3M E-A-R Classic (29dB), Howard Leight MAX (33dB)
REQUIRED - When equipment noise exceeds 85 dBA per OSHA 29 CFR 1910.95
Safety Footwear Steel-toed, slip-resistant, ASTM F2413 REQUIRED - At all times in equipment areas per site safety policy

TOOLS REQUIRED

Specific tools required for Carrier Water Cooled Chiller Annual Preventative Maintenance based on equipment type and task:

Tool Category Specific Tools Purpose
Refrigerant Service Tools • Recovery machine (EPA certified)
• Vacuum pump (2-stage, 5 CFM min)
• Digital manifold gauge set
• Electronic leak detector
Refrigerant service and leak detection for Carrier Water Cooled Chiller
Temperature & Pressure • Infrared thermometer
• Thermocouple probe set
• Differential pressure gauge
• Psychrometer
Temperature and pressure measurements for Water Cooled Chiller diagnostics
Mechanical Tools • Socket set (metric and standard)
• Pipe wrenches
• Tube cutters and flaring tools
• Fin comb set
Mechanical service on Carrier Water Cooled Chiller components
Electrical Test Equipment • Multimeter
• Clamp meter
• Capacitor tester
• Motor rotation tester
Electrical testing of Water Cooled Chiller controls and motors
Safety Equipment • Lockout/tagout kit
• First aid kit
• Fire extinguisher (appropriate class)
• Emergency eyewash (if chemicals present)
Safety equipment required for all maintenance work
Specialized Carrier Tools Manufacturer-specific tools required per Carrier 19XRV5P51442LCH64S service manual

SAFETY PROCEDURES

Procedure Requirements Initials Time
Pre-Work Safety Briefing Conduct safety briefing with all personnel, review hazards specific to Carrier Water Cooled Chiller maintenance, verify PPE
Lockout/Tagout (LOTO) Follow site LOTO procedure per OSHA 29 CFR 1910.147 for Water Cooled Chiller isolation
Hot Surface Warning Allow Water Cooled Chiller to cool before service, use thermal protection if required

EMERGENCY CONTACTS

Emergency Type Contact Phone Number
Medical Emergency Emergency Medical Services 911
Fire Emergency Fire Department 911
Chemical Emergency Poison Control / CHEMTREC 1-800-222-1222 / 1-800-424-9300
Facility Emergency
Equipment Manufacturer Carrier Technical Support

LOCAL EMERGENCY SERVICES

Location: 2300 US-34, Oswego, IL 60543

✓ RESEARCHED: The contact information below has been researched for this specific location. Please verify current phone numbers before use as they may change over time.
Service Contact Name Phone Number Address
Local AHJ (Authority Having Jurisdiction) Village of Oswego Building & Permits Department 630-554-2310 100 Parkers Mill, Oswego, IL 60543
Nearest Hospital Rush Copley Medical Center 630-978-6200 2000 Ogden Ave, Aurora, IL 60504
Fire Department (Non-Emergency) Oswego Fire Protection District, Station #1 630-554-2110 3511 Woolley Road, Oswego, IL 60543
Police Department (Non-Emergency) Oswego Police Department 630-554-3426 3355 Woolley Road Oswego, IL 60543
Local Utility - Electric ComEd 800-EDISON1 (800-334-7661) 24/7 Emergency Line
Local Utility - Gas Nicor Gas 888-Nicor4u (888-642-6748) 24/7 Emergency Line
CRITICAL: Work shall NOT proceed until safety briefing is completed and all required PPE is verified available. All personnel must sign the safety briefing attendance sheet.

Section 06: MOP Assumptions

Key Project Assumptions

Category Assumption
Equipment Condition Chiller is operating within normal parameters as defined by Carrier's O&M manual, with no known pre-existing mechanical faults (VERIFY WITH MANUFACTURER for specific model).
Spare Parts Availability Commonly required spare parts (filters, belts, gaskets, oil) are readily available on-site or can be procured within a reasonable timeframe (SITE-SPECIFIC REQUIREMENT based on criticality and lead times).
System Redundancy System has N+1 redundancy, or a backup chiller is available, allowing maintenance to be performed without critical disruption of cooling services (SITE-SPECIFIC REQUIREMENT).
Environmental Conditions Ambient environmental conditions (temperature, humidity, air quality) are within the chiller's specified operating range as defined in the Carrier O&M manual.
Personnel Qualifications Maintenance personnel are certified HVAC technicians with specific training and experience on Carrier water-cooled chillers, including refrigerant handling certification per EPA regulations.
System Documentation Up-to-date and accurate system documentation, including the Carrier O&M manual, as-built drawings, and maintenance logs, are available and readily accessible to maintenance personnel.
Resources All required test equipment is calibrated and available on-site
Infrastructure The facility's electrical and mechanical infrastructure can support equipment isolation without affecting other critical systems
Management Management approval has been obtained for the maintenance window and potential risks have been communicated to stakeholders

Critical Decision Points for Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C):

Section 07: MOP Details

Date Performed: Time Begun: Time Completed:
Facilities personnel performing work:
Contractor/Vendor personnel performing work:

Chiller Operational Data Log

Parameter Compressor 1 Units
As FoundAs Left
Voltage L1-L2 VAC
Voltage L2-L3 VAC
Voltage L1-L3 VAC
Current L1 Amps
Current L2 Amps
Current L3 Amps
Oil Level %
Discharge Temp °F
Suction Temp °F
Discharge Pressure PSIG
Suction Pressure PSIG
Chilled Water Temp In °F
Chilled Water Temp Out °F

Chiller Performance Data

Parameter As Found As Left Units Acceptable Range
Chilled Water Flow Rate GPM Per design specs
Condenser Water Flow Rate GPM Per design specs
kW Input kW Per nameplate
Cooling Capacity Tons Per nameplate

System Fault/Alarm History

Date/Time Fault/Alarm Code Description Action Taken Initials

Detailed Procedure Steps

Step Detailed Procedure Initials Time
1 Notify Data Center Operations Manager, Site Security, and NOC/BMS Operator that procedure is about to begin
2 Notify relevant personnel of the planned Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C) preventative maintenance.
3 Verify backup chiller system is operational and ready to assume cooling load.
4 Record baseline operating parameters of Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C): entering/leaving water temperatures, pressures, and flow rates. (SITE-SPECIFIC REQUIREMENT)
5 Initiate Lockout/Tagout (LOTO) procedure for Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C) electrical supply and water lines according to OSHA standards and site-specific LOTO procedures.
6 Verify zero energy state for all electrical components of Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C) using appropriate testing equipment (multimeter).
7 Ensure proper Personal Protective Equipment (PPE) is worn: safety glasses, gloves, and any other required PPE based on site-specific safety regulations.
8 Inspect the area around the Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C) for any potential hazards: leaks, obstructions, or unsafe conditions.
9 Close chilled water supply and return valves to isolate the Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C).
10 Drain the water from the chiller barrel. Refer to Carrier manual for specific drain locations and procedures.
11 Inspect chiller barrel for scale, corrosion, and fouling.
12 Clean chiller tubes using appropriate brushes and cleaning solutions. REFER TO Carrier MANUAL for approved cleaning agents.
13 Rinse the chiller barrel thoroughly with clean water to remove any remaining cleaning solution or debris.
14 Inspect all water box gaskets for damage or wear and replace if necessary.
15 Reinstall water boxes, ensuring proper alignment and sealing.
16 Refill the chiller barrel with treated water.
17 Inspect refrigerant lines for leaks, damage, and corrosion.
18 Verify refrigerant type (R-134a or R-410A) for Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C) and refrigerant level.
19 If refrigerant level is low, check for leaks using an electronic leak detector. Repair any leaks before adding refrigerant. FOLLOW EPA GUIDELINES.
20 Record refrigerant pressures (high side and low side). VERIFY ACCEPTABLE RANGES WITH MANUFACTURER (Operating parameters: 120-150 PSIG (high side), 30-50 PSIG (low side)).
21 Inspect compressor for oil leaks, damage, and unusual noise or vibration.
22 Check compressor oil level and add oil if necessary. VERIFY OIL TYPE WITH MANUFACTURER.
23 Analyze compressor oil sample for contamination (moisture, acid, debris). (SITE-SPECIFIC REQUIREMENT)
24 Inspect and clean compressor motor windings.
25 Check compressor motor winding resistance and insulation.
26 Inspect and clean condenser coils. Remove any debris that may restrict airflow.
27 Check condenser fan motor for proper operation and lubrication.
28 Inspect and clean electrical control panel.
29 Tighten all electrical connections in the control panel. Torque values: 40-50 ft-lbs (electrical) - VERIFY WITH MANUFACTURER.
30 Inspect and test all safety controls (high pressure, low pressure, oil pressure, water flow).
31 Verify calibration of all temperature and pressure sensors. (SITE-SPECIFIC REQUIREMENT)
32 Inspect and clean or replace air filters.
33 Check the operation of the chiller's control system.
34 Verify all control settings are correct for optimal performance. (SITE-SPECIFIC REQUIREMENT)
35 Inspect vibration isolators for damage and proper function.
36 Take vibration measurements of the compressor and motors. REFER TO MANUFACTURER SPECIFICATIONS for acceptable vibration levels.
37 Inspect and tighten all mechanical fasteners. Torque values: 25-35 ft-lbs (mechanical) - VERIFY WITH MANUFACTURER.
38 Check the alignment of the motor and compressor.
39 Verify proper grounding of all electrical components.
40 Verify all maintenance tasks are completed and documented.
41 Obtain sign-off from qualified personnel.
42 Remove Lockout/Tagout (LOTO) devices after verification.
43 Restore electrical power to the Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C).
44 Open chilled water supply and return valves.
45 Start the Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C) following the manufacturer's recommended startup procedure. REFER TO Carrier MANUAL.
46 Monitor the chiller's operation closely during startup.
47 Check for any unusual noises or vibrations.
48 Record operating parameters: entering/leaving water temperatures, pressures, and flow rates. (SITE-SPECIFIC REQUIREMENT)
49 Compare the current operating parameters to the baseline readings taken before the maintenance. (SITE-SPECIFIC REQUIREMENT)
50 Make any necessary adjustments to optimize the chiller's performance. (SITE-SPECIFIC REQUIREMENT)
51 Allow the chiller to run for at least one hour to stabilize.
52 Re-inspect for leaks and proper operation.
53 Document all maintenance activities performed, including any repairs or adjustments made.
54 Update the chiller's maintenance log with the date, time, and details of the preventative maintenance.
55 Notify relevant personnel that the Carrier Water Cooled Chiller (Unit: CHILLER-1, Serial: SN-A47B021C) is back in service.
56 Return any temporary equipment to its designated storage location.
57 Clean up the work area and dispose of any waste materials properly.

Critical Step Notes (Steps requiring torque verification or electrical testing):

Section 08: Back-out Procedures

CRITICAL BACK-OUT PROCEDURES

If at any point during the maintenance procedure a critical issue is discovered that could affect data center operations, follow these detailed back-out procedures:

Step Back-out Procedures Initials Time
1 Immediate Actions: Stop all work immediately and secure the area
2 Notify the Facility Technician and Lead Technician immediately
3 Assess the situation and determine if equipment can be safely returned to service
4 If issue cannot be resolved at technician level, escalate to Chief Engineer
5 If Chief Engineer cannot resolve, escalate to Data Center Manager
6 Contact equipment manufacturer service representative if required: Equipment Manufacturer Service Representative
7 Document all findings and actions taken in the incident report
8 If safe to return to service, follow re-energization procedures
9 Monitor equipment for minimum 30 minutes after return to service
10 Complete incident report and schedule follow-up maintenance if required

Section 09: MOP Approval

Review Stage Reviewer's Name Reviewer's Title Date
Tested for clarity:
Technical review:
Chief Engineer approval:
Customer approval:

Approval Requirements:

MOP Effective Date:
MOP Expiration Date:

Section 10: MOP Comments

MOP Comments

Post-Maintenance Requirements:

Additional Notes:

Section 11: References and Documentation

Comprehensive Reference Library

Equipment-Specific Documentation

Document Title Type Access
Carrier Water Cooled Chiller Documentation Technical Manual 📋 View

Safety Standards and Guidelines

Safety Standard Authority Access
OSHA 29 CFR 1910.147 - The Control of Hazardous Energy (Lockout/Tagout) OSHA 📋 View
OSHA 29 CFR 1910.95 - Occupational Noise Exposure OSHA 📋 View
OSHA Personal Protective Equipment Standards OSHA 📋 View
ANSI Z87.1 - Eye and Face Protection ANSI 📋 View
ASTM Standards ASTM 📋 View

Additional Resources

Resource Type Access
Site-Specific Emergency Response Plan Internal Document Internal Document - Request from Site Manager
Equipment History and Maintenance Records CMMS Database Internal Document - Request from Site Manager
Safety Data Sheets (SDS) Information Chemical Safety 📋 View
Environmental Compliance Documentation Regulatory Internal Document - Request from Site Manager
Vendor Contact Information and Support Agreements Service Contract Internal Document - Request from Site Manager

📚 Reference Usage Guidelines

⚠ Important Notice: All external links have been verified as working at the time of MOP creation. However, URLs may change over time. If a link is broken, search for the document by title on the organization's website. Internal documents marked "Request from Site Manager" must be obtained locally and are not available through external links.

📋 Link Verification: All links in this document point to official sources only: • Manufacturer support websites • OSHA.gov regulations • EPA.gov standards • NFPA.org codes • Industry organization websites